After 6 years, Gaza power plant operating at full capacity
Published Thursday 02/08/2012 (updated) 03/08/2012 22:23
Abu al-Omrin told reporters the plant was operating at full power.
GAZA CITY (Ma'an) -- The power authority in Gaza announced Thursday it is capable of operating the sole generator in the enclave at full capacity for the first time in six years.

The generator is only operating at full power -- 100 megawatts -- at night. During the day it is working at 60 megawatts to conserve fuel, a spokesman for the energy authority Ahmad Abu al-Omrin said at press conference in Gaza City.

It would require 600,000 liters of fuel daily to operate the plant at full strength 24 hours a day, Abu al-Omrin said.

Energy needs have increased in Gaza in recent years due to population growth and urban development, he said, and the enclave needs 360 megawatts of electricity daily.

Abu al-Omrin thanked the Islamic Bank for funding the rehabilitation of the power plant, which was damaged by Israeli military operations in 2006 and 2008.

He also thanked Egypt and Qatar for supplying fuel to Gaza. The delivery of Qatari fuel, which began in July, eased a power crisis which had caused power cuts of up to 18 hours a day.

The official said the restoration of the power plant made it imperative for stakeholders -- particularly Egypt -- to make sure enough fuel was allowed into Gaza to run it.

He urged officials to implement an agreement to link Gaza's electricity grid to Egypt's and to lay down a network of pipes to supply fuel to Gaza via the Rafah crossing on Egypt's border.

The Qatari fuel has been delivered via Egypt and Israel through Palestinian Authority intermediaries.
Print Send to friend
1 ) Billy Bragg / UK
03/08/2012 08:26
......''which was damaged by Israeli military operations in 2006 and 2008.'' Be a shame if Hamas repeatedly fire rockets at Israel, so that the generator becomes damaged again.

2 ) gaza girl / gaza strip
04/08/2012 01:04
Good job....i had 1 full day of electricity and then it went off for 11 hours. It took them 6 years....for what? More lies and propaganda. Makes me sick.
Name Country
Comment
Characters
Note: Comments will be reviewed for appropriate content. Click here for more details.

Share/Bookmark

Mursi orders military operation to free hostages
Man killed in Gaza tunnel collapse
Palestinian killed, 2 hurt in Lebanon clash

Close Next Previous
All Rights Reserved © Ma'an News Agency 2005 - 2013